Safety information search results
Filter your results
Building height
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Locations
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS Newsletter 4 (1)
- CROSS-AUS Newsletter 5 (2)
- CROSS-AUS [sub-heading only] (2)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 18 (1)
- CROSS-UK Newsletter 35 (2)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 42 (1)
- CROSS-UK Newsletter 44 (1)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK [sub-heading only] (12)
- CROSS Newsletter (11)
- CROSS Safety Report (18)
- News [sub-heading only] (1)
CROSS regions
Precast concrete demolition
During the demolition of a tower block, a column collapsed unexpectedly.
1 March 2006
CROSS Safety Report
Report ID: 27
Region: CROSS-UK
Grouting of joints between load-bearing prefabricated concrete members
This report highlights the risk of failure if grouted joints between load-bearing prefabricated concrete members are not designed and installed correctly.
30 April 2021
CROSS Safety Report
Report ID: 961
Region: CROSS-AUS
The use of cast-in ferrules as structural connections
This report highlights several problems that can arise with structural connections between elements when cast-in ferrules (also known as threaded inserts) are used for the anchorage of reinforcing bars.
30 April 2021
CROSS Safety Report
Report ID: 993
Region: CROSS-AUS
Collapse of a hollow core unit
This refers to the collapse of one modest span precast hollow core concrete unit and the excessive deflection of others on a building which was under construction.
1 October 2012
CROSS Safety Report
Report ID: 258
Region: CROSS-UK
Gain in strength of mortar slower than concrete
A masonry wall settled and cracked after four courses of Engineering grade B bricks were substituted (not by the designer) for the original in-situ concrete padstones on cost and handling grounds.
1 April 2010
CROSS Safety Report
Report ID: 177
Region: CROSS-UK
Composition of new precast concrete blocks
A UK firm has raised concerns over a new large precast concrete block range which seems to use a wide range of secondary recycled aggregates in its mix, including some potentially hazardous waste.
1 July 2014
CROSS Safety Report
Report ID: 380
Region: CROSS-UK
Actively seeking to identify hazards
A reporter investigating a near miss incident raises concerns that an active prompt to seek out hazards is not being undertaken on innovative construction design and methods.
1 April 2016
CROSS Safety Report
Report ID: 530
Region: CROSS-UK
Responsibilities for hybrid concrete construction
Concerns are raised after a substantial precast element, weighing over 10t, had been placed in position and used as part of the shuttering for an in-situ pour without it being designed to act as a shutter.
1 October 2016
CROSS Safety Report
Report ID: 574
Region: CROSS-UK
Failure of precast concrete cover slab to circular shaft
A reporter describes how several precast concrete cover slab units collapsed shortly after being installed.
1 April 2015
CROSS Safety Report
Report ID: 505
Region: CROSS-UK
Partial failure of precast concrete tank unit on installation
Concerns are raised after the foot of a precast concrete unit failed during installation, making the unit unstable.
1 April 2017
CROSS Safety Report
Report ID: 626
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.