Safety information search results
Filter your results
Building or structure type
Building height
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Method of construction
Structural form
Plant & equipment
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Theme pages
CROSS regions
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Poorly applied external insulation on buildings
This report concerns external insulation on buildings being inadequately applied and fixed, with poor control of the workmanship standards, leading to potential safety concerns and damage to the property.
21 August 2023
CROSS Safety Report
Report ID: 1203
Region: CROSS-UK
'Design' for alterations to a dwelling carried out by an unsuitable person
A reporter was called upon to review a design for the removal of a loadbearing wall during the refurbishment of a residence. A builder was already on site but had stopped work since they considered the engineering design to be unsatisfactory and the structural designer was not responding to their queries. The reporter found that the structural design being followed was far from competent.
21 August 2023
CROSS Safety Report
Report ID: 1236
Region: CROSS-UK
Large Panel System (LPS) building structural refurbishment issues
A reporter from a firm of consulting engineers’ comments on his experiences when refurbishing 1960s Large Panel Structure (LPS) buildings around 2000.
1 July 2011
CROSS Safety Report
Report ID: 201
Region: CROSS-UK
Temporary works propping
A reporter raises concerns about the adequacy of temporary works that were installed on site during the refurbishing of a large office building.
1 January 2010
CROSS Safety Report
Report ID: 146
Region: CROSS-UK
Inadequate chimney support
The supports for a domestic chimney had been removed which left a 2.5m high chimney stack almost unsupported and in a potentially dangerous state.
1 April 2009
CROSS Safety Report
Report ID: 131
Region: CROSS-UK
Dangerous building work on domestic project
Temporary propping fails during works to a semi-detached property putting the whole building at risk of collapse.
10 March 2022
CROSS Safety Report
Report ID: 1062
Region: CROSS-UK
Inadequate design for basement works
An inadequate structural design for alterations to a basement led to structural distress within a substantial five-storey townhouse.
21 November 2022
CROSS Safety Report
Report ID: 1132
Region: CROSS-UK
Toughened glass failures
The number of failures of heat-soaked toughened glass leads to a finding that the glass produced by some processors has not been properly heat-soaked and is therefore much more likely to shatter in use.
17 November 2022
CROSS Safety Report
Report ID: 1135
Region: CROSS-UK
Stunts on bridges cause concern
A thrill-seeker travelling up and over the arch of a bridge, risking serious injury to themselves and others, raises the concerns of a reporter.
17 November 2022
CROSS Safety Report
Report ID: 1136
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.