Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Structural steel - reinforced concrete interface
A reporter describes how the substructure of a building was constructed out of position to the extent that the steel frame could not be erected to tolerance and could not be connected to the holding down bolts.
1 March 2006
CROSS Safety Report
Report ID: 19
Region: CROSS-UK
Very slender props
A reporter noticed prop that did not have ties installed while carrying out a site inspection.
1 July 2007
CROSS Safety Report
Report ID: 34
Region: CROSS-UK
Grouting of joints between load-bearing prefabricated concrete members
This report highlights the risk of failure if grouted joints between load-bearing prefabricated concrete members are not designed and installed correctly.
30 April 2021
CROSS Safety Report
Report ID: 961
Region: CROSS-AUS
Column stability during erection
A reporter highlights the importance of ensuring steel columns are temporarily supported until they are sufficiently tied and supported by the permanent structure.
13 December 2021
CROSS Safety Report
Report ID: 1038
Region: CROSS-UK
Split responsibilities on temporary bracing of steelwork
A contractor removed temporary bracing on site prior to the structure being in a permanent stable state.
1 July 2010
CROSS Safety Report
Report ID: 204
Region: CROSS-UK
Concern about rebending starter bars
This report concerns the bending and rebending of starter bars on site during the construction of a multi storey tower. The reporter considered that such a practice could compromise the structure under extreme load conditions.
24 May 2023
CROSS Safety Report
Report ID: 1164
Region: CROSS-UK
Alteration to historic column bases causes settlement issues
Historic timber columns settled and tilted after unauthorised changes were made to their foundation bases.
1 October 2014
CROSS Safety Report
Report ID: 458
Region: CROSS-UK
Lack of experience on steel column erection
A reporter highlights how works progressed on site without a detailed method statement being provided by the contractor even though it had been requested.
1 April 2013
CROSS Safety Report
Report ID: 324
Region: CROSS-UK
Dangerous alterations to steel beam supports
A local authority building control officer went to site and witnessed on an upper floor that the columns had been removed out of sequence, before the new frame had been constructed.
1 October 2015
CROSS Safety Report
Report ID: 479
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.