Safety information search results
Filter your results
Building or structure type
Building height
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Locations
CROSS regions
Permanent formwork to slabs
Concerns are raised over deflection issues that are not being considered when using permanent formwork.
1 January 2011
CROSS Safety Report
Report ID: 215
Region: CROSS-UK
Compatibility at RC column to slab joint - strong column/weak slab
A reporter who was reviewing the structural design of a commercial building raises concerns over the compatibility at column/slab joints when different grades of concrete are used.
1 April 2012
CROSS Safety Report
Report ID: 296
Region: CROSS-UK
Safety issues with composite metal deck floors
A contractor had a near miss when pouring a concrete slab with permanent formwork.
1 January 2012
CROSS Safety Report
Report ID: 288
Region: CROSS-UK
Car park staircase collapse at construction joint
The top flight of a staircase to a multi-storey concrete car park collapsed approximately 10 years after construction.
1 July 2008
CROSS Safety Report
Report ID: 106
Region: CROSS-UK
Demolition risks
This report is about the collapse of a flat slab building that occurred overseas whilst the top floor of the building was being demolished onto the next floor down.
1 January 2008
CROSS Safety Report
Report ID: 96
Region: CROSS-UK
Responsibilities for hybrid concrete construction
Concerns are raised after a substantial precast element, weighing over 10t, had been placed in position and used as part of the shuttering for an in-situ pour without it being designed to act as a shutter.
1 October 2016
CROSS Safety Report
Report ID: 574
Region: CROSS-UK
Computer analysis and slab design twisting moments
A reporter has noticed on many occasions when checking reinforced concrete and post-tensioned slab designs that engineers often neglect to consider twisting moments when arriving at slab design moments.
1 October 2014
CROSS Safety Report
Report ID: 441
Region: CROSS-UK
Retaining wall excavation collapse
A 6m deep excavation formed for constructing a retaining wall on a domestic project collapsed due to insufficient propping.
1 July 2019
CROSS Safety Report
Report ID: 800
Region: CROSS-UK
Checking reinforcement before concrete pours
A reporter shares their concerns about incorrect rebar positioning on site prior to concrete being poured.
1 July 2020
CROSS Safety Report
Report ID: 894
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.