Safety information search results
Filter your results
Building height
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Locations
Content type
- CROSS-AUS Newsletter 2 (1)
- CROSS-AUS Newsletter 3 (2)
- CROSS-AUS Newsletter 5 (2)
- CROSS-AUS [sub-heading only] (3)
- CROSS-UK Newsletter 9 (1)
- CROSS-UK Newsletter 11 (1)
- CROSS-UK Newsletter 18 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 41 (1)
- CROSS-UK Newsletter 42 (1)
- CROSS-UK Newsletter 44 (1)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK [sub-heading only] (16)
- CROSS Newsletter (12)
- CROSS Safety Report (29)
CROSS regions
Failure of cast-in lifting eye on L-shaped wall
During a routine lifting operation of a L-shaped wall unit, one of the legs on a cast-in lifting eye which was located on top of the unit pulled out of the concrete.
1 January 2018
CROSS Safety Report
Report ID: 638
Region: CROSS-UK
Toppling of precast concrete unit during lifting causes serious injury
During a routine lifting exercise of a precast concrete unit, the unit tipped over while a worker was unslinging the top sling points for the unit using a ladder, causing them a serious injury.
1 April 2017
CROSS Safety Report
Report ID: 642
Region: CROSS-UK
Failure of cast-in lifting anchor on precast twin-wall
A precast reinforced concrete twin-wall panel was being lifted when one of the cast-in lifting anchors suffered a brittle failure.
1 January 2018
CROSS Safety Report
Report ID: 637
Region: CROSS-UK
Inadequate billets used in precast concrete connections
Whilst completing a third-party design appraisal, a correspondent found that solid steel billets intended to form the primary shear transfer mechanism between concrete beams and columns were insufficient for this purpose.
1 April 2019
CROSS Safety Report
Report ID: 705
Region: CROSS-UK
Casting, transporting and installing precast concrete kerbs
A reporter shares their experience of how collaborative engineering thinking involving several parties enabled a design solution to be found that could be constructed safely.
1 October 2018
CROSS Safety Report
Report ID: 778
Region: CROSS-UK
Design responsibility for temporary stability of steel frame building
A reporter raises concerns about the division of responsibility for the temporary stability of a four-storey steel frame structure with precast concrete planks and a structural topping.
1 April 2019
CROSS Safety Report
Report ID: 789
Region: CROSS-UK
Dislodged finger plate on highway bridge
A correspondent received a report about a 1.5m long section of a steel finger plate expansion joint on a highway bridge that had been inadequately fixed and became dislodged.
1 February 2020
CROSS Safety Report
Report ID: 879
Region: CROSS-AUS
Design and erection of prefabricated (precast) concrete
A correspondent considers that there should always be an experienced temporary works designer for prefabricated concrete structures as many structural engineers do not consider the erection methodology when designing such structures.
1 February 2020
CROSS Safety Report
Report ID: 871
Region: CROSS-AUS
Safety concern about the design of thin concrete walls
The reporter raises their concern about the design of thin concrete load-bearing walls, sometimes supporting 10 or more storeys.
1 July 2019
CROSS Safety Report
Report ID: 815
Region: CROSS-AUS