Safety information search results
Filter your results
Building or structure type
Materials
Products
Project or lifecycle stage
Design
Fire incident response
Project type
- Alteration & conversion project (3)
- Assessment project [sub-heading only] (5)
- Conservation & restoration project (1)
- Construction project [sub-heading only] (30)
- Demolition project (5)
- New build (21)
- Refurbishment (2)
- Remediation project (4)
- Repair project (2)
- Strengthening project (1)
- Structural assessment (8)
Method of construction
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS Newsletter 4 (2)
- CROSS-AUS [sub-heading only] (3)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 3 (1)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 9 (3)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 18 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 26 (2)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 31 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 41 (2)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK Newsletter 58 (5)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (28)
- CROSS Newsletter (16)
- CROSS Safety Report (60)
- News [sub-heading only] (5)
CROSS regions
Girder collapse
The failure was of a two-storey high trussed girder with a 36m span, designed to carry a composite steel and concrete floor at the lower level and a trussed roof at higher level.
1 March 2006
CROSS Safety Report
Report ID: 30
Region: CROSS-UK
Demolition risks
This report is about the collapse of a flat slab building that occurred overseas whilst the top floor of the building was being demolished onto the next floor down.
1 January 2008
CROSS Safety Report
Report ID: 96
Region: CROSS-UK
Further demolition collapse
This report is of an incident that occurred recently in a UK city when a floor suffered a structural collapse during the demolition of a reinforced concrete building.
1 January 2008
CROSS Safety Report
Report ID: 90
Region: CROSS-UK
Pre-stressing ducts
A reporter has come across a situation where during grouting of the ducts in a slab, patches of concrete as big as 0.5m x 1m and 30mm thick fell on to the ground creating a safety hazard.
1 October 2008
CROSS Safety Report
Report ID: 89
Region: CROSS-UK
Thermal effects on long span concrete car park beams
A reporter describes how long span precast hollow core units in a car park started to bow upwards due to thermal effects.
1 October 2010
CROSS Safety Report
Report ID: 173
Region: CROSS-UK
Safety issues with composite metal deck floors
A contractor had a near miss when pouring a concrete slab with permanent formwork.
1 January 2012
CROSS Safety Report
Report ID: 288
Region: CROSS-UK
Collapse of a hollow core unit
This refers to the collapse of one modest span precast hollow core concrete unit and the excessive deflection of others on a building which was under construction.
1 October 2012
CROSS Safety Report
Report ID: 258
Region: CROSS-UK
Multi-storey car parks - structural condition concerns
A reporter raises concerns about the structural condition of a number of car parks that they have worked on as remediation projects.
1 April 2012
CROSS Safety Report
Report ID: 265
Region: CROSS-UK
Effect of staff change on a design
A reporter illustrates how risk can be generated from staff turnover.
1 October 2012
CROSS Safety Report
Report ID: 277
Region: CROSS-UK
Falsework collapse during slab pour in SE Asia
There was a partial collapse of falsework on a project in Southeast Asia.
1 July 2013
CROSS Safety Report
Report ID: 337
Region: CROSS-UK