Safety information search results
Filter your results
Building or structure type
- Bridges (4)
- Buildings
(37)
- Agricultural buildings (4)
- Car parks (1)
- Commercial (5)
- Education, science & art buildings (2)
- Health care (2)
- Higher-risk buildings (1)
- Industrial buildings (1)
- Laboratory buildings (1)
- LPS buildings (1)
- Nuclear & energy buildings (1)
- Public, religious & civic buildings (2)
- Recreational buildings (1)
- Residential (11)
- Stadiums (1)
- Storage buildings (3)
- Tall buildings (3)
- Theatres & other entertainment buildings (2)
- Transport buildings (1)
- Masts & towers (2)
- Railways (1)
- Temporary structures (2)
Project or lifecycle stage
Design
Codes, standards & regulations
Fire incident response
Project type
Construction period
Method of construction
Elements & systems
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Content type
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 9 (1)
- CROSS-UK Newsletter 18 (1)
- CROSS-UK Newsletter 23 (3)
- CROSS-UK Newsletter 41 (1)
- CROSS-UK Newsletter 43 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 50 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (2)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK Newsletter 64 (1)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (16)
- CROSS Newsletter (12)
- CROSS Safety Alert (1)
- CROSS Safety Report (41)
- News [sub-heading only] (4)
CROSS regions
Checking reinforcement before concrete pours
A reporter shares their concerns about incorrect rebar positioning on site prior to concrete being poured.
1 July 2020
CROSS Safety Report
Report ID: 894
Region: CROSS-UK
Inadequate punching shear reinforcement in flat slabs
This report highlights how remedial works were required in a number of residential buildings after inadequate punching shear reinforcement was identified.
14 October 2020
CROSS Safety Report
Report ID: 950
Region: CROSS-UK
Execution not matching design assumptions
This report highlights how the connection of steel columns to twin beams acting as a transfer beam was overlooked and created an eccentric loading condition.
14 October 2020
CROSS Safety Report
Report ID: 968
Region: CROSS-UK
Lack of lateral stability in steel frame
Concerns were raised after the steel frame of a building was found to have a lack of horizontal and vertical bracing.
1 July 2016
CROSS Safety Report
Report ID: 540
Region: CROSS-UK
Shear failure during demolition
A reporter raises concerns about how a number of buildings being demolished ‘top-down’ have suffered from partial collapse during the process.
1 January 2016
CROSS Safety Report
Report ID: 523
Region: CROSS-UK
Inadequate end bearings for transfer beams
Whilst advising a steel fabricator on tendering for a transfer structure steel frame, a reporter's firm noticed a serious design error with the bearing pressures at the supports of a transfer beam.
1 October 2017
CROSS Safety Report
Report ID: 644
Region: CROSS-UK
Use of proprietary element beyond stated values
After the construction of a 6m high lighting frame, the contractor noticed that the frame was both twisting and deflecting excessively under wind loading.
1 April 2018
CROSS Safety Report
Report ID: 667
Region: CROSS-UK
Architect conducts structural design of sway frame for domestic project
A reporter looked at a project recently where the drawings had been produced by the architect, including a structural design.
1 April 2018
CROSS Safety Report
Report ID: 678
Region: CROSS-UK
Design responsibility for steel to concrete connections
A reporter provides an illustrative example to support their view that the design responsibility for steel to concrete connections should be shared between the responsible designers of both materials, and that a Lead Designer should ensure all designs are properly integrated.
20 February 2024
CROSS Safety Report
Report ID: 1261
Region: CROSS-UK
Vertical cross bracing unbolted on-site
A reporter came across a situation where a vertical cross bracing member of a temporary steel frame structure had been unbolted on-site.
10 February 2023
CROSS Safety Report
Report ID: 861
Region: CROSS-UK